Fire Protection · Compliance Report

Fire Alarm Control Panel

Fire Alarm Control Panel used in energetics production and support facilities.

Most Restrictive Requirement
UFGS 21 13 18
Preaction and Deluge Sprinkler Systems

Required Certifications

  • UL Listed
  • FM Approved
  • NFPA 20 Factory Test

Typically Missing at Submittal

  • UL Listed
  • UL 508A

Known Issues

  • Blast loading not evaluated per UFC 3-340-02
  • No RMF cybersecurity package for embedded controller

Required Standards (6)

  • UFGSUFGS 21 13 18Preaction and Deluge Sprinkler Systems
  • NFPANFPA 68Standard on Explosion Protection by Deflagration Venting
  • NFPANFPA 72National Fire Alarm and Signaling Code
  • UFCUFC 3-460-01Design: Petroleum Fuel Facilities
  • NFPANFPA 15Water Spray Fixed Systems
  • DINDIN EN 54Fire Detection and Alarm Systems

Approval Authorities

  • Electrical Safety Authority
    Electrical AHJ
  • Contracting Officer
    Procurement Authority

Used in Features of Work